Plan Review
Residential Review
Takes approximately 3 to 5 days from date submitted to Planning.
Steps:
- Submit application to the Planning Department.
- Planning distributes to Engineering for all floodplain and stormwater issues
- Inspections does final approvals before issuing Permits
Note: When submitting to Planning with application ensure that you include foundation, walls and completed roof details, Stormwater Pollution Prevention Plan and Floodplain Permit (where applicable). These must be in the plans in order for the Inspections department to issue the building permit.
Related Topics: Residential Building Application
Floodplain Permit Application
Stormwater Pollution Prevention Plan (PDF)
Commercial Review
Takes approximately 5 to 15 days from date submitted to Planning.
Steps:
- Submit application to the Planning Department.
- Planning distributes plans to the Engineering, Fire Marshals and Inspections department for review.
- Once all reviews are completed and signed off the Inspections department will complete their review and sign off and issue Building Permit.
Note: Due to the commercial being more complex for review please ensure that at least one set of plans is wet stamped and signed by Architects and Engineers, following complete code analysis listed above.
Related Topics: Commercial Building Application
Floodplain Permit Application